Terra-Gen Closes Financing For Second Phase Of Edwards Sanborn Solar Storage Franchise In California
Sep 16, 2022•almost 3 years ago
Description
Terra-Gen, LLC, a leading independent renewable energy provider, has completed financing on the second phase of its Edwards Sanborn Solar Storage facility in Kern County, Calif., a project that will produce clean energy for more than 164,000 homes and displace more than 320,000 tons of CO2 annually. This phase of the Edwards Sanborn Solar Storage facility is composed of 410 MWac of (megawatts, alternating current) of nameplate solar capacity (358 MWac at the point of interconnection) and 1,786 MWh (megawatt hours) of battery storage. The first phase of the Edwards Sanborn project was financed in July 2021 and its 345 MW of PV and 1,505 MWh of storage are now fully operational.